Town of Bristol Water Distribution Expansion
Location: West Street & Lovers Lane Water Distribution Expansion
Services: Funding Source Assistance, Preliminary Engineering, Final Design & Construction
Phases, Subsurface Planning Study and General Consulting
Point of Contact: Ms. Valerie Capels, Town Administrator
Year: 2014, 2017, 2018
In 2014, Jamie Simpson successfully designed and administered a water distribution repair contract that addressed several identified leak locations from an independent water system leak evaluation. This contract included an extension of approximately 300 linear feet of new 4-inch diameter water main, replacement of five (5) house service connections, a replacement of an existing gate valve at a street intersection, replacement of a tee connection at a different street intersection, and a new house service connection on the existing 6-inch cast iron distribution main.
In 2017, Jamie assisted the Town with improvements to West Street from the intersection with Maple Street to Airport Drive. The project involved roughly 4,000 feet of new water main and water main replacement, stormwater drainage improvements, and concrete sidewalk replacement. A cross-country water main extension from West Street to Lovers Lane was also part of the project.
Preliminary Engineering, Final Design, Construction Contract Documents, Permitting, Bid Phase Services, were all provided. Resident Representative services were provided in 2017 and 2018.